Turkey Creek Ph 2 - Interceptor

Image
8:00am- another manhole is arriving this morning and crew will unload it and possibly use it here at MH E51 location. There is only a couple degrees different in flowline angle. Crew was originally going to grout today, but then manhole was in route.  9:11am- manhole E50 is unloaded and is getting test fit to pipe at E51 location. Crew has decided to wait on another manhole for E51 location to be built.  9:44am- crew returns back to grouting jere at MH E20. All grouting downstream from here is complete except for MH E2.  11:44am- crew is finishing up MH E20 grouting and will call it a day.