Turkey Creek Ph 2 - Interceptor
6:58am- crew will continue with pipe and encasement work here at E-04. 8:07am- crew will now be moving the last two joints placed yesterday due to a rolled gasket. 8:42am- 3rd joint back has to come out. Its where the bad gasket was at. 9:07am- new joint getting installed back now. 10:53am- so, after a long morning the 1st new joint of the day is set. Dirt work under the bridge is back underway today also. 1:10pm- 4th joint placed for today and final top cages going on pipe for encasement. Concrete to be jere at 3pm. 3:10pm- 6th joint placed for today and still awaiting concrete. 3:45pm- concrete begins. 4:33pm- This will round out the day here. Concreting will continue.