Turkey Creek Ph 2 - Interceptor
Crew to set MH E32 today. 8:39am- Manhole bases are being unloaded from haul truck first thing this morning… 10:02am- now rebar is being unloaded for encasement that will be built. 11:02am- crew setting MH E32. 11:50am- manhole E32 now connected with a 12’ piece of pipe. Line is also lamped back to MH E31. 1:24pm- MH E32 is stacked out and alignment to next manhole is underway. 2:30pm- rebar is now getting tied for cages. 3:22pm- two halves almost built. 4:37pm- 4 halves now built and they will riund out the day on the 5th.