Turkey Creek Ph 2 - Interceptor
7:08am- crew is back digging to lay more pipe today upstream of MH E5. 8:29am- 1st joint of the day is now in place. 9:37am- 2nd now placed. 11:02am- 3rd full joint plus a 7 footer now installed. 12:42pm- 4th full joint in now. 2:03pm- 6th full joint now getting gravel. 3:15pm- 7th full joint placed. 4:37pm- 8th full joint is in, but rock will need broke now. This will round out their day here.