Turkey Creek Ph 2 - Interceptor
7:15am- crew will finish digging out for MH E39 first thing this morning. 8:20am- crew messes up a gasket on the last pipe laid yesterday. They will dig it out and replace the pipe now. 9:56am- joint of pipe is now replaced and crew cuts pipe to fit at manhole connection to line. -10:00am: meet with Tom Head and Terry Snowden on Ph 2 under the bridge to discuss some issues still on Ph 1 and additional concerns on PH 2. 12:37pm- MH E39 is set and tied to line now with two joints s now placed upstream of it. 2:18pm- #7 joint of pipe going for the day so far now. 4:40pm- Joint #11 is in with gravel going in for #12 to round out the day here.