Turkey Creek Ph 2 - Interceptor
Line flushing will be finishing up today, and more cleanup will occur. 7:23am- cleanup at MH E20 is underway this morning. More rock removed at MH 14. 1:00pm- flushing of the line is now completed and crew will now move back to MH E13 area to tie in pipe. Cleanup is almost done now up to MH 23. 2:39pm- back on line now at MH E13 to get pipe tied together. 3:32pm- grading gravel. 3:53pm- 1st joint now in place. 3+ joints to go to reach MH E13. 4:02pm- bank cabe in! 4:48pm- 2nd joint placed for today and this will end the day. Bigger rock to stabilize grade closer to manhole E13 will be hauled in in the morning.