Turkey Creek Ph 2 - Interceptor

Image
7:00am- top cage to go on top of last pipe set yesterday. Another 3 full joints +8’ to end of encasement.  7:46am- breaking rock.  8:48am- digging out for joint of pipe now.  9:42am- wrapping and strapping is done on MH E11 now.  10:41am- 1st joint of the day placed with rebar top cage going on yesterday’s last pipe laid.  12:15pm- 2nd now in with underlying cage.  2:04pm- 3rd joint in with cages being placed atop.  3:04pm- concreting begins.  3:55pm- 2 loads of concrete now placed.  4:31pm- more concrete is on its way to finish up encasement on across the creek. This will round out the day.