Posts

Showing posts with the label 12-1-2021

Turkey Creek Ph 2 - Interceptor

Image
Crew will move MH E46 from quarry yard to end of Carlton Rd first thing this morning.  7:35am- manhole E46 will be loaded in truck after E26 is removed. E26 was replaced early on due to flowline issue.  8:40am- now back at MH E45 area to begin pipe work for today.  9:24am- 1st joint going in and getting gravel.  9:51am- 2nd joint.  10:22am- 3rd. 10:54am- joint #4.  11:42am- #5.  12:04pm- #6 is placed.  1:42pm- crew is done ar MH E32 pulling pipe used for culvert so that they can lay two more joints on toward E46 today.  3:00pm- 7th joint now being placed.  3:45pm- 8th joint goes in as this will end the pipe laying until more pipe arrives onsite. We are very mear MH E46 now. The plug will be placed in the end of the pipe until they return.  3:59pm- more brush pules are lit on fire today along line.  4:25pm- dozer work in the bottoms to round out the day.