Turkey Creek Ph 2 - Interceptor
6:14am- crew is back to digging this morning to lay more pipe again today. 8:15am- no pipe set yet. Water coming into ditch creating issues for laser. Some rock was broke out also. 9:10am- grading gravel to lay first joint of the day. Wrapping and strapping continues on MH E7. 10:06am- breaking rock for second joint. 11:03am- 2nd joint is now placed. 1:16pm- 3rd joint now set n place. A lot of water continues to enter the ditch. 2:10pm- still digging on 4th joint for today and MH E4 gets a 2’ barrel section added and will be wrapped and strapped. 3:13pm- 4th joint now placed with plug going into the end of pipe for the weekend. Crew calling it a day due to the overtime worked on creek crossing. Backfill occurring to keep pipe from floating.