Turkey Creek Ph 2 - Interceptor
7:11am- rock will be hauled in first thing to prep sub grade of ditch line onto MH E13. 7:45am- 2” clean rock will be placed in ditch once more material is removed. 9:35am- bench is having to be cut back so that pipe can be slid in far enough to join main line once last joint is placed. 10:54am- more flowline bench will be removed in order for the pipe to enter further in for main line connection. 11:30am- pipe is now joined to MH E13 and main line. Essentially, 4 joints were used for tie in total. 2 yesterday and two today. Line is also lamped by laser back to MH E12. 12:00pm- backfill will now occur. 1:17pm- crew lights a brush pile on fire at this time. 2:37pm- dozer work being done to get things cleaned up jere at MH E13 area. 3:07pm- crew is going to call it a day. Equipment is moved back to south end of project where pipe laying will begin Monday!