Turkey Creek Ph 2 - Interceptor
7:03am- crew unloads barrel section and lid for MH E49. The temporary barrel section will be removed and replaced with new. 7:29am- now digging from E47 to E48. 39’ run. 9:14am- joint placed coming up out of MH E47. 11:03am- grading gravel for next joint. 12:53pm- last pipe going in now to finish run. 1:19pm- 3 joints now placed now between MH E47 and E48. Interceptor is now completed. Line is also lamped. 1:44pm- backfill and rough in underway. 3:10pm- MH E49 getting right barrel section now. 3:56pm- grading work on shoulder of roadway. 4:48pm- another look at roadway as crew pulls up spoil material from bank side of roadway.