Turkey Creek Ph 2 - Interceptor

Image
7:03am- crew unloads barrel section and lid for MH E49. The temporary barrel section will be removed and replaced with new.  7:29am- now digging from E47 to E48. 39’ run.  9:14am- joint placed coming up out of MH E47.  11:03am- grading gravel for next joint.  12:53pm- last pipe going in now to finish run.  1:19pm- 3 joints now placed now between MH E47 and E48. Interceptor is now completed.  Line is also lamped.  1:44pm- backfill and rough in underway.  3:10pm- MH E49 getting right barrel section now.  3:56pm- grading work on shoulder of roadway.  4:48pm- another look at roadway as crew pulls up spoil material from bank side of roadway.