Turkey Creek Ph 2 - Interceptor
Pipe laying picks back up today. Crew has laid two joints from MH E16. 9:20am- well, crew is now pulling out the 6 joints laid today back to MH E16. They did not check the flow line to ensure manhole was made right. The flow line is backwards with a 1.5” difference. Wire is being pulled from under the gravel and removed. Right hand side of picture is inlet side. 9:55am- MH E16 now removed. Crew will send rest of the day moving manholes and clearing more of R.O.W. 1:03pm- gate going in off of Branson Creek road for access to project so that they can start closing off area again. 2:38am- more wrapping and strapping occurring today.