Turkey Creek Ph 2 - Interceptor

Image
More cleanup and culvert change outs here on Carlton today.  8:41am- getting dirt pulled up and out of trees along steep side of roadway.  9:58am- 18” culvert getting installed now between E55 & 54 manholes on roadway.  10:39am- culvert now going in between MH E51&50.  11:40am- last culvert going it between MH E49&48.  12:58pm- grader work on Carlton continues.  2:10pm- more dirt is getting pulled up from edge of roadway near MH E48.  2:17pm- base rock now getting applied to roadway.  4:10pm- standing at MH E47 looking down line. More cleanup occurring downline now.  Looking down Carlton Rd from E48. Grader work still progressing.