Turkey Creek Ph 2 - Interceptor
6:55am- crew getting set back up to begin laying more pipe today. 7:35am- digging is now underway. Crew will place another rebar cage encasement near MH E2 as concrete will occur this afternoon on both encasements. 7:50am- joint #1 going in now. 8:54am- #2 going in. Delay in posting due to start up ar LS6 Branson Creek Ph 2. All went well! 11:25am- cage is placed under joint #4 today with 5th joint ready to go in. 11:45am- top cage in now and getting tied to bottom cage. 1:30pm- 6th joint placed as crew digs for setting MH E2 now. 2:46pm- MH E2 is set and stacked. Concrete also going in on both encasements now. 3:27pm- line from E2 back to E1 is lamped by daylight. 4:19pm- concrete is finished on the one encasement closest to MH E2. 4:56pm- 1st concrete encasement now almost completed. This will round out the day with wrapping and strapping on E2.