Turkey Creek Ph 2 - Interceptor
7:08am- crew will continue with RipRap here at MH E11-E12 today as well as more strapping of manholes along the route. 8:29am- Strapping now occurring at MH E12. 9:53am- dirt is getting spread near MH E7. 10:58am-MH E12 now backfilled around and more riprap to be placed here at E11. 11:54am- more rings getting bolted down today. 2:00pm- more gravel to be removed feom MH E18 today after flushing the line again. 3:54pm- more dirt is being hauled in to MH E6-E7 areas. 4:13pm- walked field under bridge to look at “clover” coming up, but was unable to locate any. 4:57pm- dirt still being applied.