Turkey Creek Ph 2 - Interceptor

Image
6:58am- crew is back this morning to lay more pipe and set MH E41 today.  7:32am- rock is encountered so Jack hammer is back on.  8:30am- 2 joins are now placed this morning.  9:42am- 4th in working on #5.  10:42am- 5th joint is placed and MH E41 is getting graded out for setting.  11:30am- MH E41 is now set with a 13’ piece of pipe tying it to the line.  Line is also lamped by laser back to MH E40.  1:45pm- alignment to MH E42 is complete and the 2nd joint out of E41 is getting gravel. 8 joints laid so far today.  3:10pm- manholes are being unloaded here at site today.  4:16pm- 12 joints of pipe laid so far now.  5:05pm- crew will get joint 15 for today.