Posts

Showing posts with the label 5-26-2021

Turkey Creek Ph 2 - Interceptor

Image
7:47am- Crew is back laying pipe and will be at MH E25 today setting it.  8:53am- 2nd joint getting gravel.  10:34am- 4th joint being placed.  1:08pm- MH E25 is almost ready to set. Crew will move manhole upstream about 9.5’ to help clear the vertical rock wall adjacent to the dig line.  2:00pm- MH E25 base now set with another full joint connecting it to the line. 5 joints laid so far today.  Line is also lamped by laser back to MH E24.  3:00pm- MH E25 is stacked up now as alignment to MH E26 takes place with transit.  3:51pm- 1st joint now laid out of MH E25. 6th joint for the day.  4:50pm- crew has laid 8 joints total for today. Excavator will move to begin backfill.