Turkey Creek Ph 2 - Interceptor
7:45am- gravel is done at MH E31 as crew will level-it up and set the base section next. 9:41am- MH E31 is now set and rock is getting broke out for first joint of pipe to be laid. Line is lamped back to MH E30 also. 12:03pm- 2 joints now placed upstream of MH E31. 1:56pm- 5 joints now placed so far. 3:03pm- joint #6 getting gravel. 16:02pm- 7th joint in digging for 8th one today. MH E30 also being wrapped at this time. 4:43pm- graveling #8 now. This will wind up the day with backfill to occur.