Turkey Creek Ph 2 - Interceptor
7:11am- Crew is back today to lat more pipe and get MH E40 set. 8:33am- 2 joints have now been placed this morning. 10:03an- 5 joints now placed and digging for MH E40 is next. 11:10am- grade is checked at MH E40. 2” low. 11:50am- MH E40 is now tied to line with a 12’ piece of pipe. Line is lamped back to E39. This picture is from MH E39 looking downstream to MH E38 today. I forgot to post it yesterday. 1:57pm- 1st joint placed upstream of E40 now. 3:34pm- 3rd joint upstream of E40 almost ready to go in for a total of 10 joints so far today. 4:29pm- joint 11 goes in. 5:05pm- high rock is encountered. Jack hammer will be put on for first thing in the morning.