Turkey Creek Ph 2 - Interceptor

Image
7:10am- crew is back digging to lay more pipe today as they are about half way to MH E38 from E37.  8:04am- joint #2 going in.  8:40am- #3 getting placed.  10:33am- joint #6 going in.  12:00pm- 8 joints laid so far today.  1:21pm- #10 getting gravel.  2:42pm- MH E38 is set with another joint of pipe make 11 joints thus far. Bell was removed to allow manhole.  Line is lamped back to MH E37.  3:25pm- crew making alignment to MH E39 now.  4:55pm- two joints out of MH E38 for a-total of 13 joints placed today. This will round out the day.