Turkey Creek Ph 2 - Interceptor
6:57am- crew took measurements for pipe last evening and cut a 10.5’ piece of pipe to tie MH E35 to line segment. Crew will set manhole today and work on getting slope anchors drilled and tied up. 7:51am- MH E35 is now set in place and line is lamped by laser back to MH E34. Slope anchors also going in at this time. 9:55am- 1st joint out of E35 is getting placed while rock is dumped upon hillside so loader doesn’t have to haul it from bottom of the hill. 11:35am- 4th joint going in with rain falling. 11:50am- crew calls it a day!