Turkey Creek Ph 2 - Interceptor
6:45am- Blasting crew is back to begin blasting in area of MH E1- E6. Flatcreek crew will be bringing equipment from E33 area this way to start laying pipe. 9:43am- more manholes now unloaded. 10:22am- well the Blasting company is taking a different approach to all the creek gravel… 11:15am- Crew is now backfilling behind where the Blasters are working so that they can begin digging to lay pipe. 12:54pm- pipe is now getting moved down line towards E1 location. 2:30pm- Opened E1 manhole to check to see of plug was still in place after close proximity of blasting. Looks good. Not leaking. 4:15pm- area now backfilled back to E1 fromE3 location. 4:35pm- pipe is getting moved now to roadway from under bridge so that lasting can continue once they get that far.