Turkey Creek Ph 2 - Interceptor

Image
7:11am- drizzle has stopped as crew sets laser back into MH E36 to begin laying pipe.  9:20am- 2 joints of pipe now placed and MH E37 is dug and a measurement for pipe is happening now! 10:00am- a 11’ piece of pipe now ties MH E37 to line.  Line is lamped back to MH E36.  11:42am- 3rd joint now being placed upstream of MH E37 as alignment is being checked.  12:49pm- a total of 6 joints +11’ are now placed.  2:50pm- crew re-checking alignment again with 10 joints +11’ now placed.  4:25pm- joint#15 +11’ going in now. This will round out the day here.  Backfill continues.