Turkey Creek Ph 2 - Interceptor

Image
7:01am- crew will fall back and finish up slope anchors and get them ready for concrete around noon. Big boulders will be getting broken up so that they are more manageable.  9:11am- crew working on last slope anchor with drilling in the rebar.  10:32am- going back now and installing plywood for concrete on lower side of anchors.  12:38pm- concrete going in now on slope anchors between MH E34-35.  2:11pm- backfill of pipe above MH E35 is underway as they await more concrete to arrive for slope anchors.  2:40pm- concrete is now completed! 3:35pm- 1joint placed with MH E36 getting prepared for entry.  4:15pm- MH E36 is set with a 5’ piece connecting it to the line.  Line is lamped back to MH E35.  5:01pm- crew aligning next MH run to E37.  5:10pm- 1st joint is s placed out of MH E36 now. Gravel will follow to round out the day.