Turkey Creek Ph 2 - Interceptor
7:10am- line work will pick back up today with line being approximately 100’ from MH E27. 7:51am- 1st of the day getting gravel. 9:50am- digging for 4th joint now. 11:14am- digging for #8. 12:23pm- pump getting set up for setting of MH E27. 12:38pm- top going on E26. 2:25pm- MH E27 base now set with a five foot section. 8joints + 5’ so far today. Line lamps by laser back to MH E26. 4:30pm- a partial joint goes in as crew manages a total of 10 joints combined today. Backfill will begin to round out the day.