Turkey Creek Ph 2 - Interceptor
Once haul truck is back running, crew will continue with riprap and cleanup here today under bridge. 8:48am- truck is back running and dirt was hauled to low spot under bridge. Dirt to be spread out later today. Crew is back to moving ground. 10:16am- creek is taking shape again. 11:28am- more riprap now going in on MH E6 side. 1:22pm- MH E6 is getting adjusted back down 2’ so that the surrounding ground can be graded to it. 2:14pm- barrel section now changed out. 2:53pm- wrapped and strapped! 3:51pm- Terry Snowden stops by site today. Still wants the right grass seed to be sowed. 4:21pm- riprap beginning at MH E11- E12 crossing. This will round out the day.