Turkey Creek Ph 2 - Interceptor
7:33am- crew back to digging this morning to lay more 27” pipe.
8:31am- 2 joints laid so far this morning.
9:05am- 3rd pipe placed.
9:54am- 5th joint being placed.
11:00am- 7th joint being placed.
1:03pm- working to set joint 10 as wrap is put on MH E14.
1:34pm- crew has lost target down pipe and is currently trying to retrieve it...
2:08pm- target is retrieved and joint 11is placed.
3:00pm- 13th joint now being placed.
4:00pm- dozer begins backfill process on line laid today.
5:05pm- 18th joint laid today. Crew will be picking up and calling it a day.