Turkey Creek Ph 2 - Interceptor
7:06am- Crew will have to haul in more pipe and rock first thing this morning.
8:24am- one load of gravel and one bundle of pipe is all thats been hauled down to site so far. Crew will work til noon to get materials down to line, then resume digging.
12:31pm- crew prepares to resume digging now as they are near the encasement at E-05.
2:07pm- 3rd joint getting placed.
3:00pm- 4th joint placed, and now dug out for gravel, blocks, and rebar before next pipe placement. But, first a pump is needed to evacuate the water so gravel can be graded out.
3:40pm- pumping occurring and rebar cage has to be adjusted after the hauling of it to the site location.
4:55pm- crew will work on other half the f rebar cage and get the diesel 4” pump set up and call it a day.