Turkey Creek Ph 2 - Interceptor


Crew will be pumping water first thing and fixing roadway coming off hill at quarry. 
12:18pm- crew will begin here shortly with trying to get grade, blocks and rebar placed for encasement E-05. 

12:57pm- ditch is stabilized with shot rock and gravel placed over it. 

1:43pm- Blocks and rebar placed. 

Pipe in and to grade. 

2:14pm- 2nd joint laid today. 

3:36pm- top cage getting tied to bottom. 

3:50pm- digging out for MH E15 now. 3 joints laid for today so far. 

5:05pm- crew sets MH E15 and ties it to line with a 10’ section approximately. 
All looks right!