Crew encases pipe today with concrete at E-05.
The are nearest camera will be left open due to rebar not covered and additional concrete will be placed here on next pour.

12:38pm- 3 joints of pipe are laid so far today upstream of MH E15.

2:10pm- more strapping going on MH E14.
3:20pm- crew has laid 9 full joints and an 8’ piece that was left over on a cut.
12:38pm- 3 joints of pipe are laid so far today upstream of MH E15.
1:40pm- 5th joint getting placed.
2:10pm- more strapping going on MH E14.
3:20pm- crew has laid 9 full joints and an 8’ piece that was left over on a cut.
They are calling it a day due to them working late the other night.