Turkey Creek Ph 2 - Interceptor
Crew is back laying pipe today.
8:02am- grading gravel for 3rd joint.
9:33am- joint 6 is now placed.
11:30am- joint 11 is now placed as crew is almost at MH E16.
1:05pm- joint 12 is laid and digging to set MH E16 now.
3:05pm- crew back to setting manhole abd shooting grade. Excavator had to go unload manholes at quarry.
4:31pm- 13 joints laid and MH E16 base is set. Gravel backfill and next run setup will round out the day.
MH E16 to E15.