Turkey Creek Ph 2 - Interceptor


Pipe laying picks back up today. Crew has laid two joints from MH E16. 

9:20am- well, crew is now pulling out the 6 joints laid today back to MH E16. They did not check the flow line to ensure manhole was made right. The flow line is backwards with a 1.5” difference. 

Wire is being pulled from under the gravel and removed. 

Right hand side of picture is inlet side. 

9:55am- MH E16 now removed. 

Crew will send rest of the day moving manholes and clearing more of R.O.W.  
1:03pm- gate going in off of Branson Creek road for access to project so that they can start closing off area again. 

2:38am- more wrapping and strapping occurring today. 