Turkey Creek Ph 2 - Interceptor
Line work will continue today as crew will be approaching MH E17.
7:20am- top is being placed on MH E16 first thing this morning.
8:30am- 1st joint now placed.
10:23am- joint 6 going in now.
MH E16 has been wrapped and strapped now.
12:57pm- MH E17 base is now set with 102’ od PS46 pipe laid.
E17 - E16.
2:36pm- now headed out of MH E17.
4:50pm- crew has laid 170’ of pipe today and set MH E17 base; being about 4 joints upstream of the manhole.