Turkey Creek Ph 2 - Interceptor


Crew will be attempting to lay pipe today if they can maneuver in the mud. 
8:55am- crew will be laying pipe. I will have to end up riding down in the haul truck later today for inspection. They will keep sending pictures to me as they progress. 1st joint placed so far today. 

9:35am- 2nd joint in place. 

3:19pm- 9th joint laid as backfill begins. Area for MH E18 also dug out at this time. 

4:55pm- MH E18 ready to slip onto pipe now. 

5:03pm- line is lamped. 