Turkey Creek Ph 2 - Interceptor
Crew will work to lay pipe today.
8:00am- equipment getting fueled now that the creek crossings have been traversed.
Lid to manhole E17 is getting set.
8:37am- digging to lat 1st joint and to get ligned up for next run from E18.
10:10am- 1st joint placed and aligned. Gravel now being placed over pipe from yesterday.
10:32am- MH E17 getting wrapped and strapped.
11:00am- 4th joint going in now.
12:00pm- crew has decided not to dig anymore due to encasement that needs to be done. Rain is in the forecast on Sunday and they don't want the mud and silt to enter ditch.
I will be headed offsite.