Turkey Creek Ph 2 - Interceptor
Crew will begin laying pipe today from MH E13.
7:48am- crew starts the day with pumping water and gravel banks caving in.
8:38am- MH E13 base is now set.
10:23am- 2nd joint now placed.
11:20am- joint 4 going in.
1:05pm- preparing for joint 8 so far today.
2:30pm- digging for 13 while backfill is now underway respectively.
3:00pm- crew lays joint 13 and will stop for today due to them running out of gravel.