Turkey Creek Ph 2 - Interceptor


Crew will begin laying pipe today from MH E13. 
7:48am- crew starts the day with pumping water and gravel banks caving in. 



8:38am- MH E13 base is now set. 

10:23am- 2nd joint now placed. 

11:20am- joint 4 going in.

1:05pm- preparing for joint 8 so far today. 

2:30pm- digging for 13 while backfill is now underway respectively. 



3:00pm- crew lays joint 13 and will stop for today due to them running out of gravel. 