Turkey Creek Ph 2 - Interceptor
More pipe to be laid today after a shot from yesterday is knocked down so haul truck can deliver gravel.
8:40am- gravel is getting hauled now and crew will prepare to lay pipe.
9:10am- 1st joint of the day!
9:35am- 2nd joint.
9:53am- 3rd going in.
11:03am- joint 6 now placed.
11:58am- crew has hit non-blasted rock. Lid to MH E13 will be set.
Crew will fetch the breaker from Branson Creek area and begin breaking rock.
1:21pm- hammer has now arrived onsite.
2:16pm- still breaking rock. Light rain also begins.
2:55pm- the 7th joint finally going in after the rock breaking.
4:10pm- joint 9 in place as hammer will be back breaking rock before next joint can be laid.
I will be headed offsite now for a meeting with Mr. Rittenhouse.