7:25am- crew is back digging to lay more pipe today. The total of 10 joints were laid yesterday. Today a little more rock breaking to occur and the setting of MH E14 will take place.  

8:37am- 1st joint for today. 

10:09am- 2nd joint is placed as rock is broke for the setting of MH E14. 

12:42pm- a 11&3/4 ft piece of pipe is placed so that a 5’ section can be added at manhole E14 connection. 

2:06pm- MH E14 now placed as crew aligns for next run. 

3:13pm-4th joint now laid for today, being the 1st out of MH E14. 

4:20pm- crew has laid a total of 5 joints +2.75’ and set MH E14. Backfill will now take place. 