Turkey Creek Ph 2 - Interceptor


Crew will attempt to lay pipe today with  a lot of mud and water present. 
7:50am- pump is set up now as water gets evacuated from hole. 

9:07am- 2nd joint so far getting placed. 

10:40am- 5 joints now laid. 

11:50am- 6 joints laid as crew now lays out blocks for encasement E7. 

1:12pm- 8 joints on laced with 20’ of bottom rebar for encasement placed. 

2:20pm- encasement with concrete is mow underway. 

4:38pm- encasement completed and manhole E21 base now set with a full joint of pipe. 9 joints total for today. 