Turkey Creek Ph 2 - Interceptor
Crew will attempt to lay pipe today with a lot of mud and water present.
7:50am- pump is set up now as water gets evacuated from hole.
9:07am- 2nd joint so far getting placed.
10:40am- 5 joints now laid.
11:50am- 6 joints laid as crew now lays out blocks for encasement E7.
1:12pm- 8 joints on laced with 20’ of bottom rebar for encasement placed.
2:20pm- encasement with concrete is mow underway.
4:38pm- encasement completed and manhole E21 base now set with a full joint of pipe. 9 joints total for today.