Turkey Creek Ph 2 - Interceptor


Crew will work to lay more pipe and do encasement E6 between MH E18-19. 
7:56am- blocks are being placed for grade on pipe in area of 20’ encasement E6 this morning. 

9:37am- encasement rebar is now laced and tied and awaiting concrete now. Equipment will track up to bridge to haul back bucket loads of concrete to place on pipe. 

10:14am- concrete begins. 

11:13am- 9 yds now placed. A call back is needed to finish it out. 

12:30pm- encasement almost complete. More pipe is being laid as crew awaits more bucket loads. 5 joints now placed so far today. 

1:14pm- concrete now done. 

1:20pm- digging out for MH E19. 

4:00pm- MH E19 now set and 8th joint for today goes in leaving E19. 

5:00pm- crew laud 10 joints today total. 