Turkey Creek Ph 2 - Interceptor
Crew will work to lay more pipe and do encasement E6 between MH E18-19.
7:56am- blocks are being placed for grade on pipe in area of 20’ encasement E6 this morning.
9:37am- encasement rebar is now laced and tied and awaiting concrete now. Equipment will track up to bridge to haul back bucket loads of concrete to place on pipe.
10:14am- concrete begins.
11:13am- 9 yds now placed. A call back is needed to finish it out.
12:30pm- encasement almost complete. More pipe is being laid as crew awaits more bucket loads. 5 joints now placed so far today.
1:14pm- concrete now done.
1:20pm- digging out for MH E19.
4:00pm- MH E19 now set and 8th joint for today goes in leaving E19.
5:00pm- crew laud 10 joints today total.