Turkey Creek Ph 2 - Interceptor


7:45am- crew getting pump running this morning to pump water from hole and start laying pipe upstream of MH E21. 

8:55am- 1st joint placed and aligned; now begins 80’ encasement area, E-08. 

9:55am- to much water running in from top so pipes will be placed across ditch to divert it. 



11:18pm- 3 joint of pipe placed now as rebar cage top sections begin going in place with bottoms already set under pipes.  

1:30pm- 60’ of the rebar and pipe have been placed for concrete. Light rain begins now. Haul trucks will be bringing concrete down here shortly. 

2:05pm- concrete has arrived and encasement is underway. 

2:50pm- about 30’ now encased in concrete under light rain still. 

3:50pm- the 60’ is pretty much done at this point with concrete. 



4:30pm- MH E21 is stacked on out. 

4:40pm- tracer tape is rolled across concrete encasement. Crew will be wrapping up their day. 