7:50am- Crew is back laying line at STA 66+51. Encasement E-09 will not be installed due to the depth of the line with the ground flattened out and instead a double layer of rip rap will be placed here per the Engineer. 

9:25am- 4th joint of the day is now placed. 

10:45am- 5 joints are laid as rock is being broke out for MH E23. 

12:54pm- crew is now setting MH E23 base with 5’ section tying into the 6 joints laid so far today. 

Line is lamped by laser back to MH E22.

2:25pm- two section now placed on E23 and transit set up for alignment to E24 being done now. 

2:51pm- graveling for 1st joint out of E23 now. 

3:28pm- rock will need broke out now. 

4:56pm- 3rd joint out of E23 for a total of 9 joints + 5’ for the day. Backfill will round out the day. 










 