Turkey Creek Ph 2 - Interceptor
7:07am- The excavator is headed to the top to unload manholes first thing.
8:55am- crew has laid one joint now for this morning so far.
9:51am- joint #4 getting lowered in now.
11:11am- 5 joints laid with a little rock breaking now taking place.
12:43pm- still on 5th joint, but graveling for 6th due to excavator having to go back to the top to unload more manholes being delivered.
1:56pm- digging is going good. Crew has now laid their 8th joint so far while rains continue to fall.
2:06pm- crew is done laying pipe in the rain for today. Excavator will continue to work backfilling whats been laid.