Turkey Creek Ph 2 - Interceptor
7:47am- Crew is back laying pipe and will be at MH E25 today setting it.
8:53am- 2nd joint getting gravel.
10:34am- 4th joint being placed.
1:08pm- MH E25 is almost ready to set. Crew will move manhole upstream about 9.5’ to help clear the vertical rock wall adjacent to the dig line.
2:00pm- MH E25 base now set with another full joint connecting it to the line. 5 joints laid so far today.
Line is also lamped by laser back to MH E24.
3:00pm- MH E25 is stacked up now as alignment to MH E26 takes place with transit.
3:51pm- 1st joint now laid out of MH E25. 6th joint for the day.
4:50pm- crew has laid 8 joints total for today. Excavator will move to begin backfill.