Turkey Creek Ph 2 - Interceptor
7:28am- crew will work through the mud today to lay more pipe upstream of MH E19.
8:32am- 2 joint in place so far this morning.
9:57am- #5 is laid.
11:02am- 7th joint now laid.
12:14pm- 9 joints placed as backfill is happening now.
1:44pm- joint 12 getting placed.
3:13pm- 15 joints laid today. Crew will backfill now and go put track on other excavator so that it can be used again.