Turkey Creek Ph 2 - Interceptor


7:28am- crew will work through the mud today to lay more pipe upstream of MH E19. 

8:32am- 2 joint in place so far this morning. 

9:57am- #5 is laid. 

11:02am- 7th joint now laid. 

12:14pm- 9 joints placed as backfill is happening now. 

1:44pm- joint 12 getting placed. 

3:13pm- 15 joints laid today. Crew will backfill now and go put track on other excavator so that it can be used again. 