Turkey Creek Ph 2 - Interceptor
7:10am- line work will pick back up today with line being approximately 100’ from MH E27.
7:51am- 1st of the day getting gravel.
9:50am- digging for 4th joint now.
11:14am- digging for #8.
12:23pm- pump getting set up for setting of MH E27.
12:38pm- top going on E26.
2:25pm- MH E27 base now set with a five foot section. 8joints + 5’ so far today.
Line lamps by laser back to MH E26.
4:30pm- a partial joint goes in as crew manages a total of 10 joints combined today. Backfill will begin to round out the day.