Turkey Creek Ph 2 - Interceptor
7:10am- equipment fueling before starting the day. Digging to resume at a point just upstream of MH E27.
7:45am- almost dug out for 1st joint this morning.
8:54am- 1st joint in as rock had to be broke first thing.
9:48am- 2nd joint now in place.
10:58am- 3rd pipe in as more rock is encountered that not broke from the blasting.
12:40pm- grading out for #4. More rock was broke out.
2:00pm- still on the 4th joint for today with more rock having been broke out.
3:02pm- still breaking rock. Still on 4th joint.
3:45pm- crew prepares to call it a day. All dug out for encasement work starting on Monday!