Turkey Creek Ph 2 - Interceptor
7:03am- water to be pumped down and gravel placed for blocks so encasement to be done today as MH E27 is approached.
8:26am- more rock breaking occurred and gravel grade going in for rest of pipe on encasement section.
9:07am- encasement is ready concrete!
Also at this time MH E27 is getting wrapped and strapped.
11:35am- concrete has now made it to the site!
11:53am- 1 bit of concrete now placed. More loads to follow.
12:35pm- concrete encasement now completed.
2:06pm- MH E28 is now set and line is lamped back to E27.
3:14pm- transit aligned to next manhole E28 as rock breaking occurs again.
4:04pm- changing back out to dig bucket.
4:34pm- alignment of 3rd full joint for today being the 1st out of MH E28.
Bedding going on pipe. Total pipe today is 51’ with the 9’ section tying into MH E28.
4:46pm- rock is high and will need to be broke some more for next joint. This will round out the day.