Turkey Creek Ph 2 - Interceptor


7:05am- crew will be laying pipe today from approximately 126’ upstream of MH E29. Equipment is being brought back down from top area this morning. 

8:50am- crew is now w dug out for 1st joint placement, but pump will be moved first to continue pumping water before gravel goes in. 

9:18am- 1st joint of the day getting gravel. 

10:37am- 2nd joint goes in…slow day. Awaiting tracer wire to be delivered now.

12:07pm- 3rd joint of the day getting gravel. 

1:04pm- digging out for MH E30. 

3:04pm- MH E30 going in with 8 feet of pipe to tie it into the 3 joints laid so far today. 

3:23pm- line is lamped by laser back to MH E29. 

4:44pm- 1st joint out of MH E30 now. 

4:55pm- pump has ran out of fuel. Crew will make area passable so fuel can get to pump. This will round out the day. 