Turkey Creek Ph 2 - Interceptor
Crew to lay more pipe today just upstream of MH E30.
12:49pm- crew has laid 5 joints of pipe so far today as digging continues.
1:35pm- rock had to be broke as pump is now being moved on up in the ditch.
2:47pm- 7 joints are now placed as more rock will need broke out now.
4:03pm- #8 is in place as pump is being moved again to allow for digging at MH E31 location.
4:53pm- still digging out for MH E31. Thia will round out the day here.